Meta Kansas City data center campus from the air
← All projects
Data Centers & Mission Critical

Meta Kansas City Data Center

A hyperscale campus in the Northland where material handling is the schedule — a load staged out of order stops an erection crew cold.

~1,000,000
Sq ft · first building
5.5M
Sq ft approved · 16 buildings
~1,500
Peak trade workforce
LEED Gold
Online August 2025
Challenge

Hyperscale density, phase after phase

A million square feet in the first building alone, roughly 1,500 trades on site at peak, and an erection sequence that assumes every piece is where the crane expects it.

Approach

Deliveries in erection order

Steel received, sorted and staged within crane reach in the order it gets set — not the order it arrived — with staging re-planned as each phase moved.

Outcome

Crews never waited on material

Phased structural steel operations delivered without the stoppages that a mis-staged load creates. The campus came online in August 2025.

The job

Meta's Kansas City campus sits in the Golden Plains Technology Park, north-east of I-435 and US-169, on land developed by Diode Ventures.

The first building is roughly a million square feet. The park is approved for 5.5 million across sixteen buildings, which means the site is less a project than a rolling programme — one phase erecting while the next is being received.

At that density, material handling is the schedule. Steel has to arrive in erection order and be staged where the crane can reach it on the day it is needed. A load dropped in the wrong sequence does not cost an hour — it stops an erection crew cold.

How it ran

01

Receiving and sorting

Truck-by-truck receiving against the erection sequence, with pieces sorted on arrival rather than re-handled later.

02

Staging inside crane reach

Laydown planned around the crane's working radius for that phase, so nothing needed a second pick to get where it was going.

03

Phase-to-phase handover

Staging re-planned as each building phase advanced, coordinated with Turner and the other trades sharing the same haul roads.

Data center server hall

A completed Meta data hall. Photo: Meta — not a photograph of Rucker's crews or scope. Client and project references on this page require written clearance before publication.

On a hyperscale job the crane sets the clock. Material handling either keeps it turning or becomes the reason it stops.

Our standard on mission-critical scope
Campus from the air
The completed campus in the Golden Plains Technology Park. Photo: Meta.
Data center cooling plant
Cooling infrastructure on a comparable Meta facility. Photo: Meta.

Related projects

All projects
Next case study
Gene Field Road Bridge over I-29 →
All projects

Building at hyperscale in the Midwest?

Send the erection sequence and the site logistics plan. We will come back with a competitive bid and a crew that can keep the crane turning.

Request a Bid