Data Centers & Mission CriticalMeta Kansas City Data Center
Kansas City Northland, Missouri · Meta Platforms, Inc. · Turner Construction Company · campus online August 2025
Meta's Kansas City campus sits in the Golden Plains Technology Park, north-east of I-435 and US-169, on land developed by Diode Ventures. The first building is roughly a million square feet; the park is approved for 5.5 million across sixteen buildings.
On a job at that density, material handling is the schedule. Steel has to arrive in erection order and be staged where the crane can reach it on the day it is needed — a load dropped in the wrong sequence stops an erection crew cold.
~1,000,000 sq ft
First building
5.5M sq ft
Park approved · 16 buildings
~1,500
Peak trade workforce
The completed Meta Kansas City campus. Photo: Meta. Not a photograph of Rucker's crews or scope.